# Release Planning
|
|
|
|
This document outlines our process for planning and scheduling releases, so you
|
|
can familiarize yourself with the flow of work from opening an issue to seeing
|
|
it published in a release.
|
|
|
|
## Releases
|
|
|
|
We organize releases in two ways - marketing and milestones:
|
|
|
|
- Marketing releases are what we use to represent planned features, and are
|
|
high-level goals
|
|
- **for example: 1.4, 1.5, etc.**
|
|
- Milestones are used to track issues and pull requests associated with an
|
|
upcoming release, and can be [followed on GitHub](https://github.com/desktop/desktop/milestones)
|
|
- **for example: 1.4.1, 1.4.2, 1.5.0, etc.**
|
|
|
|
We aim to ship updates to production approximately every two weeks, to ensure a
|
|
continuous flow of improvements to our users. Track our progress in the
|
|
[current milestones](https://github.com/desktop/desktop/milestones?direction=desc&sort=completeness&state=open).
|
|
|
|
## Scheduling Pull Requests
|
|
|
|
Pull Requests for user-facing changes should have a milestone associated with
|
|
them, to indicate when they should be merged.
|
|
|
|
### Features
|
|
|
|
Pull Requests associated with features for our marketing releases should have a
|
|
milestone defined as soon as possible, to indicate the anticipated release and
|
|
help track.
|
|
|
|
Pull requests for new features should leverage [feature flags](https://github.com/desktop/desktop/blob/development/docs/technical/feature-flagging.md),
|
|
so we can control when a feature is made available to users. If you are using
|
|
the GitHub Desktop [beta channel](https://github.com/desktop/desktop#beta-channel)
|
|
you will be able to help test and provide feedback about upcoming features
|
|
before they are made available to everyone.
|
|
|
|
### Bugfixes
|
|
|
|
Pull Requests associated with bugfixes or unplanned work can be opened early,
|
|
but **should not** be assigned a milestone until after they have been reviewed
|
|
and approved.
|
|
|
|
We do this as late as possible in the lifetime of the pull request to give the
|
|
maintainers an opportunity to discuss when this should be merged, and sometimes
|
|
the time and effort required to review a pull request can take it beyond the
|
|
current milestone.
|
|
|
|
The reviewer who approves the pull request may assign a milestone at the same
|
|
time to propose when this pull request should be merged, and optionally add a
|
|
comment to provide context around their choice.
|
|
|
|
These factors can be used when deciding on the chosen milestone:
|
|
|
|
- **priority** - Some bugs are more harmful (and affect more users) than
|
|
others...
|
|
- **impact** - Does this need time on the `beta` channel to verify it's good to
|
|
go?
|
|
- **timing** - Are we close to a release? Maybe it can wait a couple of days...
|
|
|
|
During the 24-hour approval window for merged pull request other maintainers may
|
|
discuss the proposed milestone (or just :thumbsup: to acknowledge and agree
|
|
with the proposed milestone).
|
|
|
|
Once the 24-hour approval window has expired the pull request can be merged by a
|
|
maintainer when the milestone corresponds with the current release.
|
|
|
|
The maintainer merging the pull request should also ensure any issues linked in
|
|
the pull request description (which will be auto-closed when merging) are also
|
|
assigned to the same milestone.
|
|
|
|
### Community Contributions
|
|
|
|
Similar to bugfixes, community PRs and features should not have a milestone
|
|
assigned until they have been reviewed and approved, and should go through the
|
|
same process.
|